Project schedule management is made up of six management processes including:activity definition, activity sequencing, (71) , and schedule control by order.
综合知识
72/75
Many useful tools and techniques are used in developing schedule. (72) is a schedule network analysis technique that modifies the project schedule to account for limited resource.
综合知识
73/75
Changes may be requested by any stakeholder involved with the project, but changes can be authorized only by (73).
综合知识
74/75
Configuration management system can be used in defining approval levels for authorizing changes and providing a method to validate approved changes.(74) is not a project configuration management tool.
综合知识
75/75
Creating WBS means subdividing the major project deliverables into smaller components until the deliverables are defined to the (75) level.